We will be removing two level crossings on Anderson Road in Sunshine, by moving the road over or under the railway. Removing the level crossings will alleviate congestion, reduce travel times and improve safety for drivers, cyclists and pedestrians.

The works will allow for the extra trains that will pass through Sunshine when the Regional Rail Link and other improvements to the public transport network are complete.

View an animation of the Anderson Road road/rail separation designs.

Level crossing locations

The two level crossings on Anderson Road are in the following locations:

North – near King Edward Avenue in Sunshine, on the Bendigo, Sydenham and freight lines

South – between Forrest Street and Sun Crescent in Sunshine, on the Ballarat line.

North design

In place of the level crossing on the Bendigo and Sydenham lines we will build:

  • a new road underpass for the Bendigo, Sydenham and freight rail lines. The railway tracks will remain at their current height and the road will be lowered to allow vehicles to travel underneath
  • a new shared-use path on the eastern side of Anderson Road, providing an uninterrupted bicycle and pedestrian connection across the Bendigo, Sydenham and freight rail lines
Existing level crossing at the Bendigo and Sydenham lines

 Existing level crossing at the Bendigo and Sydenham lines

 Level crossing - Ballarat line and Sydenham lines removed

Level crossing at the Bendigo and Sydenham lines removed

South design

In place of the level crossing on the Ballarat line there will be:

  • a regrading of Anderson Road, which will be raised slightly to allow the railway tracks to run underneath
  • a new shared-use path on the eastern side of Anderson Road, providing an uninterrupted bicycle and pedestrian connection over the Ballarat rail underpass
Existing level crossing at the Ballarat line

Existing level crossing at the Ballarat line

 Level crossing - Ballarat line removed

Level crossing at the Ballarat line removed

Benefits of removing the level crossings

  • Allows traffic to move freely and with fewer interruptions on this busy arterial road which carries about 25,000 vehicles per day
  • Removes of two level crossings which are within 500 metres of each other and close hundreds of times a day
  • Future-proofs the transport network against increased road traffic and train services - without this work, travel times along Anderson Road are expected to increase substantially
  • Improves safety for drivers, cyclists and pedestrians
  • Eliminates noise from boom gates and rail signals and reduces traffic congestion

More information

For more information or to provide feedback on Anderson Road, please contact us at any time.